Quick answer
Job costing means adding up what one job cost you and comparing it to what you charged. Use five buckets: labor with burden, materials, equipment, subcontractors and a share of overhead. In a made-up example, a 600 square foot slab quoted at $7,200 looks like 36% profit on a napkin and nets 4.6% once every cost is counted.
Construction job costing means adding up every dollar a job cost you and comparing it to what you charged. For a small concrete shop, those costs fit in five buckets: labor with burden, materials, equipment, subcontractors, and a share of overhead. One page per job.
Most owners of concrete and paving companies know their bank balance cold. Fewer know what last month’s driveway made. Below is a made-up 600 square foot slab that looks like 36% profit on the back of a napkin. Count every cost and it nets 4.6%. One slow pour day turns it into a loss.
Here is my take. Most small concrete shops don’t have a job costing problem. They have a burden and overhead problem. The cost they remember is materials plus the wages on the check, and that’s the number that makes a thin job look great.
What is construction job costing, and what goes on the sheet
Job costing is tracking every cost to the job it belongs to, then comparing the total to the price. Your profit and loss statement shows the whole company for the year. It can look fine while one slab loses money. A job cost sheet shows each job on its own, so you can see which one.
Deltek, a construction accounting software maker, puts it simply: “Your total construction job cost is the sum of all materials, labor, equipment, subcontractor costs, and overheads.” Here is what goes in each bucket.
Labor with burden
The wage on the check is not what an hour costs you. Labor burden is everything you pay on top of the wage: payroll taxes, workers’ comp, paid time off and any benefits. Pay a finisher $26 an hour at 40% burden and that hour really costs $36.40.
Sources don’t agree on a typical rate. Foreman, a construction software company, reports 25% to 45% on top of base pay. Miter, a construction payroll company, puts the average at 40%, with some contractors as high as 70%. Wiss, a CPA firm, says 40% to 70%. BLS employer cost data for construction firms show $15.84 an hour in benefits on $36.13 in wages, about 44% on top.
The range is wide because workers’ comp rates, trades and benefits differ by state and shop. So figure your own. Add last year’s payroll taxes, workers’ comp premium and any benefits you paid. Divide by last year’s gross wages. That’s your burden rate. Wiss prefers tying burden to actual hours worked over a flat percentage, but a flat rate is fine to start.
Materials and permits
Ready-mix is the big one, priced by the yard. HomeGuide’s concrete delivery guide says one yard covers about 80 square feet at 4 inches thick, and advises ordering 5% to 10% extra. Count the yards you paid for, not the yards you poured. Then add base stone, rebar or mesh, forms and stakes, cure, sealer, joint material and the permit.
Truck fees count too. HomeGuide lists short-load fees of $30 to $60 a yard under the supplier’s minimum. After a short free window, waiting time runs $2 to $5 a minute. Those charges belong to the job that caused them.
Equipment
Charge each job for the gear it used, even gear you own outright. Deltek’s advice is to use the rate you would pay to rent it. So the skid steer, plate compactor, power trowel and saw each get a day rate on the sheet. Fuel for the truck and trailer goes here too, along with dump fees.
Subcontractors
Yes, subs are part of job cost. Demo, haul-off, the pump truck, saw cutting and excavation all go on the job they worked. HomeGuide lists line pump rental at $150 to $300 an hour, with 2 to 4 hour minimums, so one pump day can swing a small job.
Watch the sub’s insurance. As one ContractorTalk poster put it: “If your sub doesn’t carry WC you pay it on his full bill.” Rules vary by state and carrier, so ask your agent. If you end up paying it, that cost goes on this job.
Your share of overhead
Overhead costs are what you pay whether or not a job runs that week. Indirect costs is another name for them: costs that keep the business going but don’t belong to one job, like insurance, truck payments, your phone, software, marketing and your own pay.
A general contractor on ContractorTalk who goes by MetroRich puts the starting point well: “Start with your business math. What are your annual overhead costs? What gross margin do you need?”
The simple way to spread overhead: divide last year’s overhead by last year’s direct job costs. That gives you a rate. Our guide to what counts as overhead and how to turn it into a markup walks through the full list.
A worked job costing example on one 600 square foot slab
Here is a made-up shop and one job. A 20 by 30 foot plain gray broom-finish slab, 4 inches thick, quoted at $7,200 ($12.00 a square foot). A sub removes the old slab. Direct cost comes to $5,724. The overhead share adds $1,145. That leaves $331, or 4.6% of the price.
The concrete math: 600 square feet at about 80 square feet a yard is 7.5 yards. The shop orders 8, about 8% extra. The crew puts in 60 hours: three people for an 8-hour prep day, four people for an 8-hour pour day, and one person for 4 hours to saw and seal. Average wage is $26, burden is 40%.
| Bucket | What is in it | Cost |
|---|---|---|
| Concrete | 8 yards delivered at $155 a yard | $1,240 |
| Other materials | Stone base $420, rebar and mesh $360, forms and stakes $180, cure, sealer and joint material $120 | $1,080 |
| Permit | City flatwork permit | $100 |
| Labor | 60 hours at $26 = $1,560 in wages, plus 40% burden ($624) | $2,184 |
| Equipment | Skid steer and plate compactor day $250, trowel and saw $150, fuel and dump fees $120 | $520 |
| Subcontractor | Old slab demo and haul-off | $600 |
| Direct job cost | $9.54 a square foot | $5,724 |
| Overhead share | 20% of direct cost ($96,000 overhead on $480,000 of direct costs last year) | $1,145 |
| Full cost | $11.45 a square foot | $6,869 |
Gross profit, after direct costs, is $1,476, or 20.5% of the price. After the overhead share, $331 is left. That’s 4.6%.
On labor share: burdened labor here is about 30% of the price and 38% of direct cost. HomeGuide’s driveway cost guide splits homeowner prices for standard and basic driveways roughly even between labor and materials. Your own sheets will tell you where you really sit.
The napkin view
Now count it the way most owners do in their head. Materials, wages with no burden, the sub and the permit. No equipment, no overhead. That’s $4,580 in cost and $2,620 in “profit,” or 36.4% of the price. Feels like a great job.
The gap is mostly burden and overhead. Burden alone is $624 on this one slab. That’s nearly twice the real profit.
What one slow pour day does
Say the pour runs 2 hours long with four people on it. That’s 8 burdened hours at $36.40, or $291. Add 30 minutes of truck waiting time, about $100 (HomeGuide puts a 30-minute delay at $60 to $150). The $331 profit becomes a loss of about $60.
Nobody on the crew did anything wrong. The job just had no room.
What the price should have been
To net 8% of the price, divide full cost by 0.92. That’s $6,869 divided by 0.92, or $7,466. Round to $7,500, which is $12.50 a square foot. Check it: $7,500 minus $6,869 leaves $631, or 8.4%.
That’s $300 more on the quote. The numbers here are made up, so swap in your own wages, tickets and overhead. The point holds either way.
Also notice $12.00 a square foot sits inside the $6 to $15 HomeGuide shows homeowners for concrete driveways overall. A price that looks normal to the customer can still be thin for you.
How to track job costs without an accountant
Use one sheet per job with the five buckets as rows. Put an estimate column next to an actual column, then a difference column. Fill it in within a week of finishing the job, while the tickets are still on the dash. Start with your last three jobs, then keep going with every new one.
The one-page sheet
You can build this job cost sheet as a template in Excel or Google Sheets, then copy it for each job. Columns: bucket, estimate, actual, difference. Rows: the five buckets, then direct cost, overhead share, full cost, price and profit. Here is where each actual number comes from.
| Bucket | Where the actual number comes from |
|---|---|
| Labor with burden | Time sheets or payroll hours for that job, times wage, times your burden rate |
| Materials and permits | Ready-mix tickets, supplier bills, receipts, permit fee |
| Equipment | Day rates for owned gear, rental invoices, fuel and dump receipts |
| Subcontractors | Sub invoices, plus any comp or liability charge from your insurer |
| Overhead share | Direct cost times last year’s overhead rate |
Three habits that keep it honest
Write hours per job on the day, by person. Put the job name on every ticket and receipt. Enter sub and supplier bills when they show up, not at month end.
The timing matters. Payroll posts Friday. The supplier bill posts whenever someone gets to it. Until every cost lands, the job looks better than it is.
On the office side of my father’s and uncle’s contracting businesses, I saw the same thing. The software was rarely the weak spot. Getting costs from the truck into the books was.
Job costing in QuickBooks, and when to move to software
If you already run QuickBooks, you may not need a spreadsheet at all. Intuit says job costing is built into QuickBooks Projects, which comes with QuickBooks Online Plus and Advanced. Projects tags time and expenses to a job and shows profit per job. Plus listed at $140 a month as of November 2026.
Most small concrete shops can stay there and just code costs to jobs better. Bigger tools make sense when you bid unit-price or public work, run certified payroll or bill with retainage. Our breakdown of construction accounting software for small contractors covers when to make that move.
How to read the result and fix the next bid
Compare two numbers to your target: gross margin after direct costs, and net profit after the overhead share. If either one misses, find the cause. It’s almost always the price, the crew hours or the type of job. Then change that one thing on the next bid.
Start with the biggest gap between estimate and actual. On each finished job, check these:
- Is your burden rate current, or from three years ago?
- Did crew hours match the estimate, prep day and pour day?
- How many yards did you order versus pour?
- Did you pay waiting time or short-load fees?
- Did the sub’s final bill match his quote?
Expect thin numbers. NAHB’s latest cost study found the average remodeler netted 6.3% after a 29.9% gross margin. Those are remodelers, and bigger firms than most concrete shops. But single-digit net is common in construction, and a gross margin has to cover a lot of overhead.
Once you know your real costs, pricing gets less scary. Another poster in that ContractorTalk thread put the usual alternative bluntly: “many (if not most) contractors do not sit down and analyze these numbers. They just charge what others charge, and hope they are charging enough.”
To turn a job cost into a price, use the markup and margin formula from last year’s books, as in this flat-rate water heater price. To feed your actuals back into the next quote faster, see our guide to estimating software for contractors.
Mistakes that make a job look better than it was
The common ones are leaving out burden, skipping equipment, forgetting overhead, logging costs late and mixing jobs on one receipt. Each one makes the job look better than it was. Then the next bid copies the same price, and the same thin margin follows you to the next slab.
Late entry is the sneaky one. Deltek lists “incomplete or delayed data entry” as a common problem, because missing hours and receipts make a job look “artificially low or high.” A ready-mix ticket that sits in the truck for three weeks makes the job look like a winner.
Coding errors do the same thing in reverse. Put two jobs on one stone receipt and one looks cheap while the other looks expensive. Neither number is real, and both bids built from them will be off.
A missed line on the quote is a cost problem too. If the old slab has to come out and the quote didn’t cover demo and haul-off, that $600 comes straight out of profit. On the example slab, that’s more than the whole $331.
Owned gear at zero is the last one. The skid steer feels free because it’s paid off. It isn’t. It wears out, needs repairs and costs money to insure. Charge every job the rental rate.
Start with your last three jobs
Today, pull the paperwork for your last three finished jobs. For each one, write down the five buckets: labor with your real burden rate, materials, equipment day rates, subs and your overhead share. Subtract from the price. See which one made less than you thought.
Then build the same sheet for the job you start next week, or for a service call such as a pool leak detection visit. Fill in the estimate column before the pour, and the actual column within a week of finishing.
Questions people ask
- What is job costing in construction?
- Job costing is tracking every cost to the job it belongs to, then comparing the total to the price. For a small shop, the costs fit in five buckets: labor with burden, materials, equipment, subcontractors and a share of overhead. It shows each job on its own, which your profit and loss statement does not.
- What is labor burden, and what is a typical rate?
- Labor burden is what you pay on top of the wage: payroll taxes, workers' comp, paid time off and benefits. Foreman reports 25% to 45% on top of base pay, Miter an average of 40% with some contractors up to 70%, and Wiss 40% to 70%. BLS data for construction firms work out to about 44% above wages.
- Are subcontractors part of job cost?
- Yes. Demo, haul-off, pump trucks, saw cutting and excavation subs all go on the job they worked. If a sub carries no workers' comp, your insurer may charge you on his bill, so that cost belongs to the job too.
- Can QuickBooks be used for job costing?
- Yes. Intuit says job costing is built into QuickBooks Projects, which comes with QuickBooks Online Plus and Advanced. Projects tags time and expenses to a job and shows profit per job. Plus listed at $140 a month as of November 2026.
- How do I include overhead in a job cost?
- Divide last year's overhead by last year's direct job costs to get a rate. If you spent $96,000 on overhead against $480,000 of direct job costs, your rate is 20%. Add 20% of each job's direct cost to that job's sheet as its overhead share.
Sources
- Employer Costs for Employee Compensation, Table 4, Private industry workers (June 2026) (2026-09-09)
- Job Costing: A Guide for Contractors and Construction Firms (Deltek) (2025-09-24)
- How Much Does Concrete Delivery Cost? (HomeGuide) (2026-05-01)
- Remodelers Saw Profit Margin Gains in 2024 (NAHB Eye on Housing) (2026-04-08)
- Markup on subcontract work (ContractorTalk) (2008-01-31)